Contract Milestone: New Gen A CA242 Concession Shell Complete
More details here
Any text changes if there are any changed or modifications to the current or upcoming phases. Milestones that are upcoming
Â
| Milestones | Start Date | Finish Date |
| New Gen A CA242 Concession Shell Complete | Â | 7/1/2027 |
| New Gen A CA214 Concession Shell Complete | Â | 7/26/2027 |
| New Gen A CA233 Concession Shell Complete | Â | 9/1/2027 |
| New Gen A CA208 – CA 211 Concession Shells Complete | Â | 11/1/2027 |
| New Gen A CA258 / CA 259 Concession Shells Complete | Â | 11/1/2027 |
| New Gen A Gaming Shells Complete | Â | 12/30/2027 |
| New Gen A Operational – Gates A1, A3, A5, A7 | Â | 1/31/2028 |
| New Gen B CB238 Concession Shell Complete | Â | 6/2/2028 |
| New Gen B CB218 Concession Shell Complete | Â | 6/29/2028 |
| New Gen B CB243 Concession Shell Complete | Â | 8/4/2028 |
| New Gen B CB208 – CB211 Concession Shells Complete | Â | 10/5/2028 |
| New Gen B CB267 / CB268 Concession Shells Complete | Â | 10/5/2028 |
| New Gen B Gaming Shells Complete | Â | 12/4/2028 |
| New Gen B Operational – Gates B2, B4, B6 | Â | 1/31/2029 |
| New Gen A Substantial Completion – All Gates Operation | Â | 2/26/2029 |
| New Gen B Substantial Completion – All Gates Operation | Â | 7/25/2029 |
| Â | Â | Â |
| Milestones | Â | Â |
| Milestone: Start Phase Zero | 12/8/2025 | Â |
| Phase Zero | 12/8/2025 | 2/13/2026 |
| Milestone: Construction NTP | 1/16/2026 | Â |
| Milestone: Start Construction New Gen A | 2/16/2026 | Â |
| Milestone: Phase 1 Start | 2/16/2026 | Â |
| Phase 1 | 2/16/2026 | 8/10/2026 |
| Milestone: Phase 2 Start | 8/11/2026 | Â |
| Phase 2 | 8/11/2026 | 12/31/2026 |
| Milestone: Start Construction New Gen B | 1/4/2027 | Â |
| Milestone: Phase 3 Start | 1/4/2027 | Â |
| Phase 3 | 1/4/2027 | 1/31/2028 |
| Milestone: Phase 4 Start | 2/1/2028 | Â |
| Phase 4 | 2/1/2028 | 4/21/2028 |
| Milestone: Phase 5 Start | 4/24/2028 | Â |
| Phase 5 | 4/24/2028 | 5/22/2028 |
| Milestone: Phase 6 Start | 5/23/2028 | Â |
| Phase 6A | 5/23/2028 | Â |
| Phase 6B | 5/23/2028 | 12/8/2028 |
| Milestone: Phase 7A Start | 12/11/2028 | Â |
| Phase 7A | 12/11/2028 | 2/26/2029 |
| Milestone: Phase 7B Start | 1/5/2029 | Â |
| Â | Â | Â |
| New Gen A | Â | Â |
| Site Prep / PBB Removal – Phase 1 | 2/17/2026 | 3/9/2026 |
| Civil – (Phases 1-3) New Gen A | 3/9/2026 | 9/3/2026 |
| Substructure Summary – New Gen A | 5/8/2026 | 9/14/2026 |
| Superstructure Summary – New Gen A | 7/31/2026 | 12/21/2026 |
| Steel Erection / PBW / Detail – New Gen A | 8/5/2026 | 11/21/2026 |
| Fireproofing – Exterior – New Gen A | 10/14/2026 | 1/13/2027 |
| Roof Buildout – New Gen A | 10/21/2026 | 3/2/2027 |
| Fireproofing – Concourse LVL – New Gen A | 10/27/2026 | 1/18/2027 |
| Envelope / Enclosure Clearstory LVL – New Gen A | 10/29/2026 | 2/23/2027 |
| Interior Buildout Concourse LVL – New Gen A | 11/6/2026 | 10/26/2027 |
| Civil – Apron Concrete (Phase 3A) New Gen A | 11/23/2026 | 1/19/2027 |
| Fireproofing – Apron LVL – New Gen A | 12/4/2026 | 12/30/2026 |
| Envelope / Enclosure Concourse LVL – New Gen A | 12/7/2026 | 5/4/2027 |
| Envelope / Enclosure Apron LVL – New Gen A | 12/21/2026 | 7/2/2027 |
| Interior Buildout Apron LVL- New Gen A | 12/23/2026 | 8/13/2027 |
| Site Finishes (Apron Scope – Phase 3) New Gen A | 5/12/2027 | 8/24/2027 |
| Civil – Apron Concrete (Phase 3B) New Gen A | 5/24/2027 | 8/24/2027 |
| Testing / CX – New Gen A | 5/26/2027 | 12/22/2027 |
| PBB’s Install & Testing – A1 – A7 New Gen A | 8/11/2027 | 9/29/2027 |
| Site Prep – Phase 4 | 2/21/2028 | 2/15/2028 |
| Civil – Apron Concrete (Phase 4) New Gen A | 3/3/2028 | 3/21/2028 |
| PBB’s Install & Testing – A9 & A11 New Gen A | 3/31/2028 | 4/20/2028 |
| Civil – (Phase 6) New Gen A | 5/23/2028 | 7/31/2028 |
| Site Prep / PBB Removal – Phase 6 | 5/23/2028 | 6/9/2028 |
| Demolition – New Gen A | 5/31/2028 | 7/10/2028 |
| Civil – Apron Concrete (Phase 6) New Gen A | 8/1/2028 | 11/2/2028 |
| PBB’s Install & Testing – A2 – A8 New Gen A | 10/27/2028 | 12/15/2028 |
| PBB’s Install & Testing – A10 & A12 New Gen A | 12/29/2028 | 1/23/2029 |
| Â | Â | Â |
| New Gen B | Â | Â |
| Civil – (Phase 3) New Gen B | 1/25/2027 | 8/4/2027 |
| Substructure – New Gen B | 4/19/2027 | 8/27/2027 |
| Civil – Apron Concrete (Phase 4) New Gen B | 7/7/2027 | 7/20/2027 |
| Superstructure – New Gen B | 7/9/2027 | 12/7/2027 |
| Fireproofing – New Gen B | 9/13/2027 | 1/13/2028 |
| Envelope / Enclosure – New Gen B | 10/15/2027 | 5/18/2028 |
| Roof – New Gen B | 11/8/2027 | 4/5/2028 |
| Interior Buildout Concourse LVL – New Gen B | 12/1/2027 | 10/12/2028 |
| Interior Buildout Apron LVL- New Gen B | 12/15/2027 | 8/14/2028 |
| Civil – Apron Concrete (Phase 5) New Gen B | 1/7/2028 | 1/20/2028 |
| Civil – Apron Concrete (Phase 6) New Gen B | 1/21/2028 | 7/24/2028 |
| Testing / CX – New Gen B | 8/10/2028 | 11/21/2028 |
| PBB’s – New Gen B | 8/15/2028 | 11/21/2028 |
| Civil – (Phase 7) New Gen B | 12/1/2028 | 12/21/2028 |
| Civil – Apron Concrete (Phase 7) New Gen B | 12/15/2028 | 1/11/2029 |
| Demolition – New Gen B | 2/2/2029 | 3/7/2029 |
| Civil – (Phase 8) New Gen B | 2/22/2029 | 4/4/2029 |
| Civil – Apron Concrete (Phase 8) New Gen B | 3/12/2029 | 5/11/2029 |
| PBB’s – New Gen B | 5/23/2029 | 6/28/2029 |
Any text changes if there are any changed or modifications to the current or upcoming phases. Milestones that are upcoming